Tech Transfer Track


PTTC recognizes that products and services featured in “Tech Transfer Track” may not be unique and welcomes information about other upstream technologies. PTTC does not endorse or recommend any of the products or services mentioned in this publication, even though reasonable steps are taken to ensure the reliability of information sources. Input can be directed to hq@pttc.org.

 Expandable Casing Reduces Drilling Costs

In developing a deep Lower Bossier play in East Texas, Burlington Resources (Burlington) faced several constraints in their well plans, including:

  • The intermediate open-hole section above the Travis Peak had to be isolated prior to entering the geo-pressured Upper Bossier section.
  • The 12 ¼-in. hole originally planned through the Travis Peak/Cotton Valley had to be reduced in size to improve drilling performance.
  • The Upper Bossier interval required isolation with a liner since the sands have a low fracture pressure and are in close proximity to the highly pressured Lower Bossier section.
  • 4 ½-in. production casing at TD was the minimum acceptable size.

Burlington chose to employ solid expandable tubulars, realizing the following benefits:

  • A 7 5/8-in. intermediate casing is typically set at the intermediate pipe point as opposed to 9 5/8-in. casing.
  • The smaller casing thus allows a 9 7/8-in. hole to be drilled through the Travis Peak instead of the 12 ¼-in. hole required for the 9 5/8-in. design.
  • The Upper Bossier is isolated with solid expandable tubulars, allowing a 6-in. hole to be drilled to TD.
  •  4 ½-in. x 5-in. production casing is run and cemented at TD.

After drilling seven slimhole wells, Burlington has found the following:

  •  The slimhole design (9 7/8-in.) improves ROP to the intermediate casing point by 37% (3.1 days per 1000 ft compared with 4.9 days per 1000 ft with larger casing).
  • Average time to TD is reduced 21%, from 94 days to 74 days. This translates into savings of about $1 million per well.

Excerpted from "Operators Address Deep Gas Drilling Challenges," Drilling Contractor, July/August 2005, p. 28.

Some New Coiled
Tubing Capabilities

Of several technologies discussed in this article about coiled tubing advances, the following concepts appeared most applicable to situations that would be encountered by independents.

Halliburton's DeepReach string uses coiled tubing sections in a single string with larger OD sections near the top and smaller OD sections near the bottom of the string. This reduces tension along the string length while sufficient flow capacity is retained. With this configuration operators can realize up to a 30% increase in depth capability compared to a conventional coiled tubing string. Specially engineered and manufactured transition joints are one key to the system. Size transition occurs in the middle of this joint. Shape and length of transition joints vary for different tubing sizes. Several field trials have been conducted, more are planned and commercialization is anticipated by year-end. The system was developed as a joint project between BP and Halliburton. Quality Tubing, Texas Oil Tools and CTES were also involved.

BJ Services' Duralink coiled tubing connector eliminates butt welds and makes connecting coiled tubing strings easier and more reliable. Connections can be installed and monitored by coiled tubing crews. To make the connection, the two ends of the coiled tubing strings are drawn into a jig, they are slid into each end of the connector and the connector is crimped to the coiled tubing. Initial effort focused on a 2 7/8-in connector, which has been successfully used in 10 jobs (as of article date). Development is ongoing for additional sizes.

Ensign Resource Service Group's coil over table design coupled with the company's Automated Drilling Rig technology. The rig design can drill with larger 3 ½-in coiled tubing as well as with conventional jointed drill pipe. With the coil over table design, tubing is bent only twice per cycle compared to six times per cycle in conventional coiled tubing operations. The capability for larger diameter tubing allows Ensign to place more drill collars on bottom, which results in straighter holes. Ensign notes that cost savings occur from: (1) using a single rig vs. two in the conventional approach (drill the hole with one rig, set casing, then move in the CT rig), (2) safe operations with a fully automated operation, (3) quick move-on, move-off with completely wheel-mounted units with dedicated tractor units and (4) time is saved with the unit's self leveling capability.

Excerpted from "Coiled Tubing Technical Advances Cut Operational Costs Sharply," Drilling Contractor, July/August 2005, pp. 36-41 available online at www.iadc.org/dcpi/dc-julaug05/July05-coiled.pdf

2005 Gulf of Mexico Studies from IHS Energy, PetroSolutions

Updating their two-year old study, IHS Energy and PetroSolutions noted new trends in deepwater Gulf of Mexico development. One key observation is the increased emphasis on channel gas reservoirs when production performance measures clearly point to sheet sands as the target of choice. Tom Harris of PetroSolutions offers these explanations: " . . . may be a function of seismic visibility, along with robust gas prices and technological advances in the areas of completions and flow assurance." In the study all 72 deepwater fields (water depth greater than 1,000 ft, reservoirs made up of deepwater facies) were analyzed. This involved analyzing 550 completions in 467 wells.

Deepwater oil reservoirs are initially undersaturated. Three primary drive mechanisms are recognized—fluid expansion, aquifer influx and formation compressibility. On an average production per completion basis, there are differences by reservoir type.

  • Sheet sands average 11,000 b/d per completion
  • Channel sands average 6000 b/d per completion
  • Channel levee sands average 4,000 b/d per completion

Using a variety of techniques, the team determined original hydrocarbons in place, expected ultimate recoverable volumes, drive mechanisms, decline rates, plateau periods, time to water breakthrough, etc. IHS believes providing this common benchmarking data allows operators to better focus efforts on specific prospects.

IHS also recently updated their study of Deep GOM reservoirs in less than 1,000 feet water depth. This study looked at more than 120 fields, discovering that the newest Deep GOM fields are outperforming their older peers. Facies were correlated with production behavior across 29 new fields. This led to discovering that certain combinations of depositional setting and facies posted higher performance by an order of magnitude.

Excerpted from "Channel Sands Shift US Gulf E&P Focus," Offshore Engineer, June 2005, p. 69 available online at www.oilonline.com/news/
features/oe/20050610.Channel_.
18255.asp
and from study information available on IHS Energy's website (
www.ihsenergy.
com/solutions/production/index.
jsp
, products and services by category).

 


Network News
4


PTTC

3rd Quarter 2005